We build the schedule nobody else wants to admit to

Katplan has fitted out and moved enterprise suites across İstanbul's Anatolian side since 2016. In that time we have learned one unpopular truth and built the whole company around it: a floor moves in an order, and that order takes weeks.

up to 2,000 m² · one phased plan module 1.20 m Surveys open

The story

Started on a weekend that did not work

In 2016 Tolga Erdoğan took on a "simple weekend move" for a trading floor in Kozyatağı. The furniture arrived before the cabling passed its tests. Desks were placed, moved, and placed again. The client occupied late, and everyone blamed everyone.

That failure became the method. Katplan plans every job as a phased week strip read straight off the floor plan — strip-out, screed, network, floor boxes, furniture, handover — and refuses to overlap the phases that physics will not let overlap. It is slower to promise and faster to deliver.

Ten years on we are a deliberately small team. Three leads who draw your plan, walk your floor, and sign your handover sheet. No call-centre, no rotating crews.

2016 · the weekend that failed

Fit-out works in progress with fresh screed and new partitions
By the numbers

Ten years, measured in floors

Not round figures — the actual ones, because that is how we work too. No star ratings and no review counts here; the record is the floors themselves.

2016 founded

on İstanbul commercial floors

3 leads

survey to handover, every job

1.2 m module

the grid every plan is drawn on

2–6 weeks

the honest length of a suite move

W1 → W6 · one phased strip

The leads

The same three people, survey to handover

Tolga Erdoğan, fit-out lead and founder

Tolga Erdoğan

Fit-out lead · Founder

K-lead-1

Civil engineer, İTÜ 2006. Seventeen years on commercial fit-outs across İstanbul before founding Katplan. Owns the W1–W4 build sequence, the module-grid setting-out and the as-built drawing set. Known on site for re-marking a grid line rather than trusting the old one.

Gül Şahin, move coordinator

Gül Şahin

Move coordinator

K-lead-2

Twelve years in logistics and building operations. Gül owns every delivery window, lift reservation and seating plan. Her signature touch is the colour-coded access schedule that keeps furniture trucks and installers from ever meeting in a loading bay.

Arda Yılmaz, network lead

Arda Yılmaz

Network lead

K-lead-3

Structured-cabling specialist, BICSI-certified since 2018. Runs every data and power pull, certifies each link, and builds the patch schedule you keep. Will not let a desk go live on an untested port — the reason furniture waits a week.

How we work

Five steps from first call to signed sheet

Step 01 — Day 1

Survey the floor

We measure against the real grid, log the raised floor, cores and access, and photograph what you have. No scope happens without a survey.

module 1.20 m~2 hours · on site

Surveying an empty office floor
Step 02 — Within a week

Draw the week strip

You get a phased plan: which week each trade is on the floor, where the floor boxes land, and a written scope. It is sent by e-mail — there is no price list and no online booking.

module 1.20 m1 drawing set · PDF

Planning the fit-out sequence
Step 03 — Weeks 1–2

Strip-out & base build

Protection up, old fit-out out, screed and partitions in. The floor cures on its own schedule — we plan around it, not through it.

module 1.20 mgrid re-marked · screed cured

Base build and screed phase
Step 04 — Weeks 3–5

Network, then furniture

Cabling pulled, tested, labelled. Floor boxes cut to the grid. Only then do furniture trucks get their booked windows and desks go in.

module 1.20 mlinks certified · seats placed

Furniture install phase
Step 05 — Final week

Snag & handover

We walk the floor with your facilities team against a written sheet, close every defect, and hand over keys, as-builts and the patch schedule.

module 1.20 m1 sheet · signed

Handover walk-through
Credentials

The paperwork behind the floors

Registered & insured

A real contractor

  • Registered contractor based in Ataşehir, İstanbul
  • Operating on İstanbul commercial floors since 2016
  • Contractor all-risk and third-party cover on every site
  • Workplace safety plan filed per project

since 2016 · İstanbul

Standards we hold to

Tested, not assumed

  • BICSI-aligned structured cabling & certification
  • TS EN 50173 link testing on every network run
  • As-built documentation issued in PDF and DWG
  • Written handover sign-off on every project since 2019
Every link certified
Ready when you are

Tell us about the floor

Book a survey and we will draw the week strip before you commit to anything.

Ask first

No price list, no online booking, no account — availability is answered by e-mail.

Answered by e-mail

Request the floor plan →